Corporate Facilities ServicesClients Graphic

Tyco Electronics (formerly Raychem)

  • AMP Production Facility Relo.: Construction of 25KSF clean production area; $1.8M
  • East End Demolition / Remediation: Demolition and clean up of obsolete bldgs; $1.5M
  • Roof Truss Repair: Repair of wooden roof truss maintain manufacturing ops; $100K
  • Building Closures: Preparation of bldgs. for sub-lease inc. wet / haz. mat. labs; $100K
  • Project Mgmt: Ongoing mgmt of multiple tenant improvement projects less than $100K

Genentech, Inc.

  • Furniture Installation & Relocation Mgmt: Ongoing mgmt services for 5k personnel

Kaiser Permanente

  • Medical Office Bldg. 1: Planning & design of 5-story medical office, 125KSF; $20M
  • Santa Teresa Medical Center: Emergency dept. expansion, 17KSF addition; $16M
  • Project Mgmt: Ongoing mgmt of multiple tenant improvement projects less than $100K

Stanford University Medical Center

  • Project Mgmt: Ongoing mgmt of multiple tenant improvement projects less than $100K

University Circle, LLC

  • University Circle: Shell construction of three 6-story class a office towers, 450KSF; $80M

Space Systems / Loral

  • B3, RF Lab Modifications: Planning, design and bidding for 100k clean room; $700K
  • B2, Rooms 300-309: Planning, design and bidding of 50KSF; $500K
  • B2, Security System Renovation: Mgmt of card reader system; $170K
  • Project Mgmt: Ongoing mgmt of tenant improvement projects less than $150K

Gap, Inc.

  • Furniture Installation & Relocation Mgmt: Ongoing mgmt services for 500 personnel

Instill Corporation

  • New Offices: 45KSF, private office and general tenant improvements + relocation; $200K

Applied Materials

  • Applied Global University: 100 KSF of major tenant improvements inc. furniture; $17M
  • B20 Corporate Offices: 96 KSF office building tenant buildout, fast track schedule; $5M
  • B78 Data Ctr Annex: 10 KSF raised floor renovation; $2M
  • B27 Office Renovation: 80 KSF of tenant improvements inc. furniture installation; $1M
  • Stewart Campus: 500 KSF in 7 buildings, shell and site construction by developer
  • Computer Ctr Expansion, Phase 2: 2.75 KSF, fm200 fire suppression, fast track; $900K
  • Computer Ctr Expansion, Phase 1: 225kva ups system, 80t HVAC, fast track; $500K
  • Server Seismic Upgrades: Equipment seismic bracing for all mainframes, servers; $400K
  • B26 Seismic Upgrades: 100 KSF building structural upgrade; $350K
  • B7 Data Ctr HVAC: Upgrade HVAC system for redundancy and finer controls; $280K
  • B28 Executive Offices: 3 KSF offices, executive furniture; $200K
  • New Data Centers: Strategic planning for new 20 KSF, 7x24x365 mainframe ops; $100K
  • Project Mgmt: Ongoing mgmt of tenant improvement projects less than $150K
  • Facilities Management: Ongoing mgmt services for 500 KSF of offices, cafes, etc.
  • Furniture Installation & Relocation Mgmt: Ongoing mgmt services for 1,500 FTE's